Displaying Consolidate Data for Entire Project Hierarchy on Project Dashboard
To get a consolidated data view of a project and all its child projects, on the project's dashboard, select the checkbox labeled as Include data from child projects, located below the project’s name link on the project's dashboard. By default, this check box is cleared.
When you select this check box, the data from a given project and all of its child projects is consolidated and displayed on the Scan Summary, Audit Progress, Security Vulnerability Exposure, License Exposure, Inventory Priority, and Inventory Review Status tiles. This data view on the dashboard helps you to provides comprehensive data for an entire project hierarchy.
If a given project doesn't include any child project, the check box labeled as Include data from child projects is disabled.
The following displays the project dashboard for a project that has child projects with the Include data from child projects check box selected: